Project details
- Project Name: Reloading Station of Klaipeda
- Country: Lithuania
- Project Location: Klaipeda
- Name of Client: Klaipedos – NAFTA
- Start Date: December 2014
- Completion Date: August 2015
- Name of Associated Firm: Baltic-Engineer
Project description
Implementation of LNG Reloading Station within the existing Oil Terminal located in KLAIPEDA – LITHUANIA; The Project consist in: – LNG Unloading facilities :
- LNG Carriers from 1 400 m3 to 25 000 m3 – Unloading flow of 1 000 m3/h.
- LNG will come from FSRU “Independance” located nearby.
– LNG Storage: Horizontal pressurized tanks of 1 000 m3 storage capacity each
- Stage 1 : 3 units
- Stage 2 : 2 additional (5 in total)
- Stage 3 : 1 additional (6 in total)
- Stage 4 : 4 additional (10 in total)
– LNG Bunkering:
- Bunkering of LNG at a maximum flowrate of 500 m3/h for oil tanker (1 000 m3) or ferries (500 m3)
– LNG Truck Loading: Loading of LNG in Trucks (50 m3 – 7 barg) up to a maximum flowrate of 100 m3/h
- Stage 1 : 3 Truck Loading Bays
- Stage 3 : 2 additional (5 in total)
– Supply Fuel Gas for Oil Terminal Boiler using Ambient Air Vaporiser and Electric Heater (100 Nm3/h to 6 000 Nm3/h)
Scope of work
- Task 1 – Technological Design Concept Study
- Task 2 – FEED and QRA
- Task 3 – EIA and Correction of Detailed Plan
- Task 4 – Reimbursable part if necessary
All Projects: