Project details

  • Project Name: Reloading Station of Klaipeda
  • Country: Lithuania
  • Project Location: Klaipeda
  • Name of Client: Klaipedos – NAFTA
  • Start Date: December 2014
  • Completion Date: August 2015
  • Name of Associated Firm: Baltic-Engineer

Project description

Implementation of LNG Reloading Station within the existing Oil Terminal located in KLAIPEDA – LITHUANIA; The Project consist in:  – LNG Unloading facilities :      

  •  LNG Carriers from 1 400 m3 to 25 000 m3 – Unloading flow of 1 000 m3/h.
  •  LNG will come from FSRU “Independance” located nearby.

– ​LNG Storage: Horizontal pressurized tanks of 1 000 m3 storage capacity each   

  • Stage 1 : 3 units
  • Stage 2 : 2 additional (5 in total)
  • Stage 3 : 1 additional (6 in total)
  • Stage 4 : 4 additional (10 in total)

– LNG Bunkering:

  • Bunkering of LNG at a maximum flowrate of 500 m3/h for oil tanker (1 000 m3) or ferries (500 m3)

– LNG Truck Loading: Loading of LNG in Trucks (50 m3 – 7 barg) up to a maximum flowrate of 100 m3/h

  • Stage 1 : 3 Truck Loading Bays
  • Stage 3 : 2 additional (5 in total)

– Supply Fuel Gas for Oil Terminal Boiler using Ambient Air Vaporiser and Electric Heater (100 Nm3/h to 6 000 Nm3/h)

 

Scope of work

  • Task 1 – Technological Design Concept Study
  • Task 2 – FEED and QRA
  • Task 3 – EIA and Correction of Detailed Plan
  • Task 4 – Reimbursable part if necessary