Project details
- Project Name : BILBAO LNG Terminal
- Country : Spain
- Project Location : Bilbao
- Name of the Client : Bilbao Bizkaia Gas Consortium (British Petroleum, Repsol, Iberdrola, Eve)
- Contract Period: 2000 – 2003
- Scope of Work : SofreGaz in joint-venture with SN Technigaz and Initec EPC LSTK : EPCC
Project Description
- Capacity: 2.7 billion Nm3/year,
- Gas grid send-out: 267,000 Nm3/hour,
- Power station send-out: 133,000 Nm3/hour.
Equipment
- LNG storage tanks: 2 x 150,000 m3,
- Cryogenics pumps: LP in-tank LNG pumps, (8 x 265 m3/hour), HP LNG pumps (4 x 243 m3/hour),
- Vaporizers: open-rack type (2 x 200,000 Nm3/hour) submerged type (1 x 200,000 Nm3/hour),
- Boil-off gas: reciprocating compressors 2 x 2,741 Nm3/hour,
- Utilities: sea water system, air, electrical power, nitrogen …,
- Auxiliaries: Flare and shutdown systems, unloading and transfer facilities, 3 x 16″ LNG unloading arms and 1 x 16″ vapor return arm, jetty for 135,000 m3 LNG tankers.