Mesdar Gas Reinjection Station

MESDAR-Flare-Gas-Recovery-sofregaz
MESDAR-Flare-Gas-Recovery-sofregaz

Project details

  • Project Name: Mesdar Gas Reinjection Station
  • Country: Algeria
  • Project Location Within Country: Mesdar
  • Start Date: 1992
  • Completion Date: 1995
  • Scope of Work : EPC LSTK: Engineering, Procurement, Construction Supervision, Commissionin
  • Contract amount: USD 51.7 million

Project Description

– LLP natural gas recovery HP natural gas reinjection,

– Inlet pressure: 50 barg,
– Outlet pressure: 360 barg,
– Gas capacity: 2 x 1.1 million Stm3/day.

 

Equipment

– Inlet network: 

16″, 56 km long pipeline (70 barg)

– Mesdar plant:

2 EGT Tornado gas turbines (5 MW each)

2 Dresser Rand multistage centrifugal compressors

– Reinjection network:

56km, 16″, 70 barg flowlines
20km, 8″, 380 barg flowlines
11km, 4″, 380 barg flowlines
12 wellheads for gas injection

 

Duration

30 months